Question: Now that tasks A and B are 1 0 0 % complete, and assuming that the work package achieved the technical / performance targets for

Now that tasks A and B are 100% complete, and assuming that the work package achieved the technical/performance targets for these two work packages, how is the project doing?
What is the schedule variance? What does this result mean?
What is the cost variance? What does this result mean?
What is the Cost Performance Index? What does this result mean?
What is the Schedule Performance Index? What does this result mean?
Take the data from above and assume that the original schedule called for the project to be completed within seven months and that the performance for the remainder of the project is similar to the performance to date.
5. What is the estimated total cost at completion (i.e., new budget)?
 Now that tasks A and B are 100% complete, and assuming

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!