Question: Now that tasks A and B are 1 0 0 % complete, and assuming that the work package achieved the technical / performance targets for
Now that tasks A and B are complete, and assuming that the work package achieved the technicalperformance targets for these two work packages, how is the project doing?
What is the schedule variance? What does this result mean?
What is the cost variance? What does this result mean?
What is the Cost Performance Index? What does this result mean?
What is the Schedule Performance Index? What does this result mean?
Take the data from above and assume that the original schedule called for the project to be completed within seven months and that the performance for the remainder of the project is similar to the performance to date.
What is the estimated total cost at completion ie new budget
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock