Question: Now that you have found the expected time and variance of activity G answer the following question: (B) Suppose this project has a single critical

Now that you have found the expected time and

Now that you have found the expected time and variance of activity G answer the following question: (B) Suppose this project has a single critical path (based on precedence relationships not shown here) and the critical path is ABEFH. (i) Describe the probability distribution for the total project time. (Tell the center (mean), shape (distribution name), and spread (standard deviation).) Keep only one decimal point. Answer: Shape = ; center = ; spread =