Question: NPV - 2nd assignment Perform a financial analysis for a project using the format discussed in course. Assume the projected costs and benefits for this
NPV - 2nd assignment Perform a financial analysis for a project using the format discussed in course. Assume the projected costs and benefits for this project are spread over four years as follows: Estimated costs are $300,000 in Year 1 and $15,000 each year in Years 2, 3, and 4. Estimated benefits are $0 in Year 1 and $220,000 each year in Years 2, and 4. No benefit in year 3. Use an 8% discount rate. Calculate and clearly display the NPV, ROI, and year in which payback occurs. Discount factor Year 1 0.93 Year 2 0.86 Year 3 0.79 Year 4 0.74