Question: number X = 8 . Then proceed to solve the following problem of Critical Path Method. Find out the following: a. Sketch the whole network

number X = 8. Then proceed to solve the following problem of Critical Path Method. Find out the following:

a. Sketch the whole network.

b. Find out critical path by analyzing and showing ES, EF, LS, LF and float in a table.

?c. Find out the project completion time.

number X = 8. Then proceed to solve the following problem of

Name of Activity Immediate Predecessors A Activity Time in Days None 5 B None C 6 A 4 D A X+6 E A F 1 E 4 G D,F H 10 B,C 8 G,H 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Economics Questions!