Question: Q2. Proceed to solve the following problem by Critical Path Method. (20) Name of Activity A B Immediate Predecessors None None A Activity Time in

Q2. Proceed to solve the following problem by Critical Path Method. (20) Name of Activity A B Immediate Predecessors None None A Activity Time in Days 5 7 7 8 D E A 1 F E 4 G H DF B,C GH 10 8 I 2 Find out the following: a. Sketch the whole network. b. Find out critical path by analyzing and showing ES, EF, LS, LF and float in a table. c. Find out the project completion time
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
