Question: o crash a schedule you should: Select one: A . Try to increase expenditures of time only those tasks that are behind schedule B .

o crash a schedule you should:
Select one:
A. Try to increase expenditures of time only those tasks that are behind schedule
B. Replace those worker that are not performing up to par with the busy.
C. Increase work efforts on those tasks that are on the critical path
D. Increase the time allowed on those tasks that have float