Question: o crash a schedule you should: Select one: A . Try to increase expenditures of time only those tasks that are behind schedule B .
o crash a schedule you should:
Select one:
A Try to increase expenditures of time only those tasks that are behind schedule
B Replace those worker that are not performing up to par with the busy.
C Increase work efforts on those tasks that are on the critical path
D Increase the time allowed on those tasks that have float