Question: (o) XYZ Ltd is currently deciding between two projects; Project X or Project Y. The projected cash flows of these two projects are given in

(o) XYZ Ltd is currently deciding between two projects; Project X or Project Y. The projected cash flows of these two projects are given in the table below: Year Project X (S) -60,000 Project Y(S) 30,000 50,000 0 40,000 0 40,000 20,000 3 20,000 Compute the net present value of each project if the opportunity cost of capital is (0) 3%. 5 marks