Question: Of the following activities from the Systems Development Process Framework, which typically requires most of a projects calendar time and budget: Iterative construction/configuration. Project planning
Of the following activities from the Systems Development Process Framework, which typically requires most of a projects calendar time and budget:
| Iterative construction/configuration. | ||
| Project planning and implementation approach selection | ||
| Functional and initial technical design. | ||
| Initial visioning. | ||
| Business analysis. |
5 points
QUESTION 42
A user story:
| Defines what capability the system should provide the user. | ||
| Generally specifies how the system should provide a feature. | ||
| Is a technical component that needs to be created. | ||
| Must be broken down into engineering tasks when creating the burndown chart. | ||
| None of the given answers are true. |
5 points
QUESTION 43
Regarding sprint capacity:
| Actual sprint capacity equals the number of team members times the number of days in the sprint. | ||
| The length of each sprint may be adjusted upward to accommodate large or complex user stories or engineering tasks. | ||
| Maximum sprint capacity equals the number of team members times the number of days in the sprint. | ||
| None of the given answers are true. | ||
| Maximum sprint capacity can be increased by adding in technical debt and staff absences and interruptions. |
5 points
QUESTION 44
As a sprint executes, the estimated effort remaining for a sprint story or task:
| Stays the same until the scrum master okays a developers progress in the stand-up meeting. | ||
| Should not be re-estimated until the planning for the next sprint has occurred. | ||
| Stays level until the story or task has been unit tested. | ||
| May go up as a developer works on the story or task, depending on actual progress. | ||
| Will stay the same until a developer begins to work on it, at which point it will decline. |
5 points
QUESTION 45
A stand-up meeting is used to conduct:
| The weekly status meeting. | ||
| The sprint retrospective. | ||
| The sprint review. | ||
| The Scrum of Scrums. | ||
| The daily meeting of project team members. |