Question: Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon

Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities.

Time (weeks) Cost ($1,000s)
Activity Description Immediate Predecessor Normal Crash Normal Crash
A Plan needs 10 8 30 70
B Order equipment A 8 6 120 150
C Install equipment B 10 7 100 160
D Set up training lab A 7 6 40 50
E Conduct training course D 10 8 50 75
F Test system C, E 3 3 60 Office Automation Inc., developed a proposal for implementing a software system that

(d) Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes cost? (A,B,C,D,E)=() (e) Develop an activity schedule for the crashed project. (f) What added project cost (in thousands of dollars) is required to meet the six-month completion time? X thousands of dollars

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!