Question: Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon
Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities.
Time weeks Cost $s
Activity Description Immediate
Predecessor Normal Crash Normal Crash
A Plan needs
B Order equipment A
C Install equipment B
D Set up training lab A
E Conduct training course D
F Test system C E
b
Develop an activity schedule.
Activity Earliest
Start Latest
Start Earliest
Finish Latest
Finish Slack
A
B
C
D
E
F
c
What are the critical activities? Enter your answers as a commaseparated list.
What is the expected project completion time in weeks
d
Assume that the company wants to complete the project in six months or weeks. What is the amount of crash time in weeks for each activity that minimizes cost?
ABCDE
e
Develop an activity schedule for the crashed project.
Activity Earliest
Start Latest
Start Earliest
Finish Latest
Finish Slack
A
B
C
D
E
F
f
What added project cost in thousands of dollars is required to meet the sixmonth completion time?
thousands of dollars
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock