Question: Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company.
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities.
| Time (weeks) | Cost ($1000s) | |||||
|---|---|---|---|---|---|---|
| Activity | Description | Immediate Predecessor | Normal | Crash | Normal | Crash |
| A | Plan needs | 10 | 8 | 30 | 70 | |
| B | Order equipment | A | 8 | 6 | 120 | 150 |
| C | Install equipment | B | 10 | 7 | 100 | 160 |
| D | Set up training lab | A | 7 | 6 | 40 | 50 |
| E | Conduct training course | D | 10 | 8 | 50 | 75 |
| F | Test system | C, E | 3 | 3 | 60 | |
(a)
Develop a project network. (Submit a file with a maximum size of 1 MB.)
This answer has not been graded yet.
(b)
Develop an activity schedule.
| Activity | Earliest Start | Latest Start | Earliest Finish | Latest Finish | Slack |
|---|---|---|---|---|---|
| A | |||||
| B | |||||
| C | |||||
| D | |||||
| E | |||||
| F |
(c)
What are the critical activities? (Enter your answers as a comma-separated list.)
What is the expected project completion time (in weeks)?
weeks
(d)
Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes cost?
(A, B, C, D, E) =
(e)
Develop an activity schedule for the crashed project.
| Activity | Earliest Start | Latest Start | Earliest Finish | Latest Finish | Slack |
|---|---|---|---|---|---|
| A | |||||
| B | |||||
| C | |||||
| D | |||||
| E | |||||
| F |
(f)
What added project cost (in thousands of dollars) is required to meet the six-month completion time?
thousands of dollars
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts