Question: Often, when you are assigned a project, the executives and/or project sponsor already have an expectation of how much the project will cost or how

Often, when you are assigned a project, the executives and/or project sponsor already have an expectation of how much the project will cost or how much time it will take. When you make an estimate early in the project without knowing much about it, that estimate is called a(n) _______________ estimate. Select one: rough order-of-magnitude inaccurate top down confidence level