Question: - Oil production factory contains a conveyor line whose function is to fill the empty bottle with oil. The job has a release time 8

- Oil production factory contains a conveyor line whose function is to fill the empty bottle with oil. The job has a release time 8 sec but the job start execution at 12 sec because of anothe function with higher priority, the deadline for this job was 19 sec from start time and the amount o time that needed to accomplish job was 9 sec. calculate: 1- Response time 2 - complete execution time 3- relative deadline 4- does the system success to fill the bottle or not