Question: ollowing are the new project implementation activities with time duration, Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 -

ollowing are the new project implementation activities with time duration,
Activity 1-21-32-43-43-54-95-65-76-87-88-98-109-10
Time in Weeks 4111654812187
Construct the CPM network
Determine the critical path and Project completion time.
Compute total floats and free floats for each activity.