Question: ollowing is a table listing the project activities, sequencing requirements and other relevant information: Expected Time Direct Cost Activity Preceded Regular Crash Regular Crash By
ollowing is a table listing the project activities, sequencing requirements and
other relevant information:
Expected Time Direct Cost
Activity Preceded Regular Crash Regular Crash
By
A days day $ $
B
C A
D B C
E D
F E
G B C
H F G
Requested:
a Construct a network including the Early and Late Start and Finish times.
b Identify the normal Critical Paths and the normal expected completion
time
c Can the project be crashed to last days? Which activities should
be crashed and at what additional cost?