Question: ollowing is a table listing the project activities, sequencing requirements and other relevant information: Expected Time Direct Cost Activity Preceded Regular Crash Regular Crash By

ollowing is a table listing the project activities, sequencing requirements and
other relevant information:
Expected Time Direct Cost
Activity Preceded Regular Crash Regular Crash
By
A --6 days 2 day $2000 $3800
B --126200010000
C A 4210004000
D B, C 10634004600
E D 8628003900
F E 6250007600
G B, C 1881600019600
H F, G 6420004000
Requested:
(a) Construct a network including the Early and Late Start and Finish times.
(b) Identify the normal Critical Path(s) and the normal expected completion
time
(c) Can the project be crashed to last 18 days? Which activities should
be crashed and at what additional cost?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!