Question: Omega 2 Project. Using the complexity weighting scheme and the function point complexity weighted table shown below, calculate the total function point count. Assume historical

Omega 2 Project. Using the complexity weighting scheme and the function point complexity weighted table shown below, calculate the total function point count. Assume historical data suggest 4 function points equal one person-month and 5 people can work on the project. (Roundanswers to the nearest whole numbers.)

Complexity Weight TableNumber of inputs8Rated complexitylow2 pointsNumber of outputs19Rated complexityaverage6pointsNumber of inquiries10Rated complexityaverage3pointsNumber of files31Rated complexityhigh11pointsNumber of interfaces60Rated complexityhigh15points

a. The total function point count is:

b. Calculate the estimated project duration:

c. If 7 people are available for the project, what is the estimated project duration?

d. If the project must be complete in six months, how many people will be needed for the project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!