Question: Omega 2 Project. Using the complexity weighting scheme and the function point complexity weighted table shown below, calculate the total function point count. Assume historical
Omega 2 Project. Using the complexity weighting scheme and the function point complexity weighted table shown below, calculate the total function point count. Assume historical data suggest 4 function points equal one person-month and 5 people can work on the project. (Roundanswers to the nearest whole numbers.)
Complexity Weight TableNumber of inputs8Rated complexitylow2 pointsNumber of outputs19Rated complexityaverage6pointsNumber of inquiries10Rated complexityaverage3pointsNumber of files31Rated complexityhigh11pointsNumber of interfaces60Rated complexityhigh15pointsa. The total function point count is:
b. Calculate the estimated project duration:
c. If 7 people are available for the project, what is the estimated project duration?
d. If the project must be complete in six months, how many people will be needed for the project?