Question: Omega 2 Project Using the complexity weighting scheme and the function point complexify weighted table shown below caiculate the total function point count. Assume historical

Omega 2 Project Using the "complexity weighting" scheme and the function point complexify weighted table shown below caiculate the total function point count. Assume historical data suggest 6 function points equal one person-month and 6 people can work on the project. (Round answers to the nearest whole numbers.) a. The totai function poirit count is: b. Calculate the estimated project duration: c. If 8 people are available for the project, what is the estimated project duration? d. If the project must be complete in six months, how many people will be needed for the project