Question: Omega 2 Project. Using the complexity weighting scheme and the function point complexity weighted table shown below, calcul the total function point count. Assume historical
Omega 2 Project. Using the "complexity weighting" scheme and the function point complexity weighted table shown below, calcul the total function point count. Assume historical data suggest 7 function points equal one person-month and 6 people can work on the project. (Round answers to the nearest whole numbers.) a. The total function point count is: b. Calculate the estimated project duration c. If 8 people are avaliable for the project, what is the estimated project duration? d. If the project must be complete in sox months, how many people will be needed for the project
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts