Question: omputerized PERT / CPM reports and charts do NOT include Part 2 A . probability estimates for on - time completion. B . cost distribution
omputerized PERTCPM reports and charts do NOT include
Part
A
probability estimates for ontime completion.
B
cost distribution tables.
C
variance reports.
D
detailed cost breakdowns for each task.