Question: On a contract that includes certified cost or pricing data, a Defense Contract Audit Agency (DCAA) audit confirm overpayments by the government of $2 million.
On a contract that includes certified cost or pricing data, a Defense Contract Audit Agency (DCAA) audit confirm overpayments by the government of $2 million. Further investigation reveals the subcontractor was aware of the Charge the prime contractor $6 million, plus interest, compounded daily, until the overpayment is repaid Charge the subcontractor $4 million, plus interest, compounded daily, until the overpayment is repaid Charge the subcontractor $2 million, plus interest, compounded daily, until the overpayment is repaid. Charge the prime contractor $4 million, plus interest, compounded daily, until the overpayment is repaid