Question: On a cpm network, activity r has two immediate predecessors, m and N . you can start to work on activity S after finishing R

On a cpm network, activity r has two immediate predecessors, m and N. you can start to work on activity S after finishing R. we know that r has a duration of 5. Ns latest finish time is 18, while Ms lastest finish time is 22. Which of the following is