Question: Qu stion 1 4 5 points On a CPM network, activity R has two immediate predecessors, M and N . You can start to work

Qustion 14
5 points
On a CPM network, activity R has two immediate predecessors, M and N. You can start to work on Activity S after finishing R.
We know that R has a duration of 5. N's latest finish time is 18, while M's latest finish time is 20. S's latest start time is 22. which of the following is definitely TRUE?
A.R is critical and has zero slack.
B. The set of times cannot all be possible.
C.S is a critical activity.
D. R has no slack but is not critical.