Question: Qu stion 1 4 5 points On a CPM network, activity R has two immediate predecessors, M and N . You can start to work
Qustion
points
On a CPM network, activity has two immediate predecessors, M and N You can start to work on Activity after finishing
We know that R has a duration of Ns latest finish time is while Ms latest finish time is Ss latest start time is which of the following is definitely TRUE?
A is critical and has zero slack.
B The set of times cannot all be possible.
C is a critical activity.
D R has no slack but is not critical.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
