Question: On January 1 , 2 0 1 7 , ABC Contractors agreed to construct a building at a contract price of 8 , 0 0

On January 1,2017, ABC Contractors agreed to construct a building at a contract price of
8,000,000. ABC estimated total construction costs would be 7,000,000 and the project
would be finished in 2019. Information relating to the costs and billings for this contract is as
follows:
Instructions
Prepare the necessary journal entries to record costs incurred, billings and cash collection
for 2010,2011 and 2012.
Using the percentage-of-completion method, compute the estimated gross profit that would
be recognized during each year of the construction period. Record the necessary journal
entries to record the gross profit for each year.
Using the cost-recovery, compute the estimated gross profit that would be recognized
during each year of the construction period. Record the necessary journal entries to record
the gross profit for each year.
 On January 1,2017, ABC Contractors agreed to construct a building at

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!