Question: On May 1, 2018, The Tomlinson started constructing a manufacturing facility completed on March 31, 2019. the following information is about the direct costs incurred
On May 1, 2018, The Tomlinson started constructing a manufacturing facility completed on March 31, 2019. the following information is about the direct costs incurred on the construction project in 2018:
May 1 /July 31 /October 30 /December 1
2,900,000 /4,200,000 /4,000,000 /160,000
All the costs were debited to "the Construction in Progress account". The Tomlinson had a loan for the project of $3,600,000 on June 1, 2018. The annual interest rate is 6%.
The Tomlinson's borrowings include: Bank loan, 6% issued March 1, 2018/ $8,000,000
Note payable 4% issued September 30, 2017 /$2,650,000
The total cost of the manufacturing facility will be recorded in the long-term asset account, 'Manufacturing Facility under construction."
Prepare the necessary adjusting entries at December 31, 2018 to record the asset and the capitalization of borrowing costs.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
