Question: On May 1, 2020 a company started constructing a manufacturing facility which was completed on March 31, 2021. You have the following information about the
On May 1, 2020 a company started constructing a manufacturing facility which was completed on March 31, 2021. You have the following information about the direct costs incurred on the construction project in 2020:
May 1 3,100,000
July 31 4,600,000
October 30 4,200,000
December 1 150,000
All the costs have been debited to the Construction in Progress account. The company took a loan for the project of $3,000,000 on June 1, 2020. The annual interest rate is 4%.
The companys borrowings include:
Bank loan, 6% issued March 1, 2020 $8,800,000
Note payable 4% issued September 30, 2019 $2,500,000
The total cost of the manufacturing facility should be recorded in the long-term asset account, Manufacturing Facility under construction.
Prepare the necessary adjusting entries at December 31, 2020 to record the asset and the capitalization of borrowing costs.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
