Question: On May 1 st , the PM sent a memo to their boss stating that Project X would require 1 3 weeks to complete (
On May st the PM sent a memo to their boss stating that Project X would require weeks to complete see network logic below activity on node diagraming at a total project cost of $K Unknown to the PM there was a contract executed whereby it was was agreed that there would be a $K penalty payment per week for every week the project exceeds six weeks.As such, the PM developed the following costing all costs are in Ks and timing matrix all timings are in weeks What is the minimum amount of additional funding beyond the project budget of $K the PM should request given the contractual penalty provision