Question: Problem 1. Draw the network and identify the critical path. Calculate the earliest-latest starting and finishing times for each activity. Also, calculate Activity Slack times

Problem 1.

Draw the network and identify the critical path.

Calculate the earliest-latest starting and finishing times for each activity.

Also, calculate Activity Slack times for each activity.

Activity

Preceding Activity

Time in Weeks

A

-

7

B

-

8

C

-

6

D

A

6

E

B

6

F

B

8

G

C

4

H

D, E

7

I

F, G, H

3

Problem 2.

Draw the network and identify the critical path.

Calculate the earliest-latest starting and finishing times for each activity.

Also, calculate Activity Slack times for each activity.

Activity

Preceding Activity

Time in Weeks

A

-

4

B

-

6

C

A, B

7

D

B

8

E

B

5

F

C

5

G

D

7

H

D, E

8

I

F, G, H

4

Problem 3.

Consider the following network (all times are in days)

  1. Drawn an activity-on-arrow network diagram representing the project.
  2. identify the critical path and associated time.
  3. What is the Network Slack time assuming the customer specification calls for the project to be completed in 21 days?
  4. Calculate the Event Slack for all events not on the critical path.
  5. What is the expected time for 68, 95, and 99 percent completion limits (i.e. the range)?
  6. Calculate the numbers of days needed to obtain a 75% confidence level the project will be complete by.

Activity

Initial Node

Final Node

Optimistic Time Estimate

Pessimistic Time Estimate

Most Likely Time Estimate

A

1

2

1

3

2

B

1

4

4

6

5

C

1

3

4

6

5

D

2

6

2

4

3

E

2

4

1

3

2

F

3

4

2

4

3

G

3

5

7

15

9

H

4

6

4

6

5

I

4

7

6

14

10

J

4

5

1

3

2

K

5

7

2

4

3

L

6

7

6

14

10

Problem 4.

Draw the network and identify the critical path.

Job Activity

Initial Node

Final Node

Estimated Time

A

1

2

2

B

1

3

3

C

1

4

3

D

2

5

3

E

2

9

3

F

3

5

1

G

3

6

2

H

3

7

3

I

4

7

5

J

4

8

3

K

5

6

3

L

6

9

4

M

7

9

4

N

8

9

3

O

9

10

2

Problem 5.

On May 1st, the PM sent a memo to their boss stating that Project X would require 13 weeks to complete (see network logic below activity on node diagraming) at a total project cost of $62K.

Unknown to the PM, there was a contract executed whereby it was was agreed that there would be a $5K penalty payment per week for every week the project exceeds six (6) weeks.

As such, the PM developed the following costing (all costs are in Ks) and timing matrix (all timings are in weeks).

Normal

Crash

Activity

Time

Cost

Time

Cost

Additional Cost per Week

A

3

$6

2

$8

$2

B

5

$12

4

$13.5

$1.5

C

5

$16

3

$22

$3

D

4

$8

2

$10

$1

E

2

$6

1

$7.5

$1.5

F

3

$14

1

$20

$3

Total

$62

What is the minimum amount of additional funding (beyond the project budget of $62K) the PM should request (given the contractual penalty provision)?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!