Question: On public projects, a design - build contract is typically awarded is based on a two - phase selection process that focus on the qualifications
On public projects, a designbuild contract is typically awarded is based on
a twophase selection process that focus on the qualifications of the designbuild team and the price
a twophase selection process that focus on price
a twophase selection process that focus on the qualifications of the designbuild team and their understanding of the project
a onephase selection process that focus on price
the lowest bidder