Question: Once the q , has been established, it is the basis for making trade - off decisions later in the project. A . work breakdown
Once the has been established, it is the basis for making tradeoff decisions later in the project.
A work breakdown structure
B process breakdown structure
C organization breakdown structure
D project priority matrix
E responsibility matrix