Question: Once you complete the week 1 3 H W assignment, please tell me which tasks are on the critical path and how long does it

Once you complete the week 13HW assignment, please tell me which tasks are on the critical path and how long does it take to complete the project. Use week 12's & 13 lecture notes as a reference for the HW and discussion for this week.
\table[[Task,Preceding Task,Duration],[Start,N/A,0 days],[F,Start,6 days],[A,Start,10 days],[B,F,10 days],[E,B,A,5 days],[D,B,4 days],[End,D,E,0 days]]