Question: Once you complete the week 13 HW assignment, please tell me which tasks are on the critical path and how long does it take to
Once you complete the week 13 HW assignment, please tell me which tasks are on the critical path and how long does it take to complete the project. Use week 12's & 13 lecture notes as a reference for the HW and discussion for this week.

Task Preceding Task Duration Start N/A 0 days F Start 6 days A Start 10 days F 10 days m CO B.A 5 days D B 4 days End D,E 0 days