Question: One month later, this engineer decides to change the sampling strategy by checking 4 0 0 boards at each sampling hour by considering the increased

One month later, this engineer decides to change the sampling strategy by checking 400 boards at
each sampling hour by considering the increased production throughput. Under this new sampling
strategy, how do you suggest for continuously monitoring such a process (selecting a c chart or u
chart) and why? Please define the random variable that follows the Poisson distribution and provide
the distribution parameter correspondingly. (0.5 point)(The processs Phase I condition is not
changed under this new sampling strategy)