Question: One reason indirect costs may be overapplied is because ___________. A. budgeted indirect costs exceed actual indirect costs B. the actual allocation base quantity exceeds
One reason indirect costs may be overapplied is because ___________.
A. budgeted indirect costs exceed actual indirect costs
B. the actual allocation base quantity exceeds the budgeted quantity.
C. requisitioned direct materials exceed budgeted material costs
D. Both A and B are correct.