Question: Only answer if you're certain and show your work, please. The R&D department is planning to bid on a large project for the development of
Only answer if you're certain and show your work, please.
The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, times, and sequences required:
| ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
| A | 4 | |
| B | A | 3 |
| C | A | 5 |
| D | A | 5 |
| E | B | 7 |
| F | C D | 6 |
| G | D F | 3 |
| H | D | 2 |
| I | E G H | 2 |
b. What is the critical path? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.)
| A-C-F-G-I | |
| A-B-E-I | |
| A-D-H-I | |
| A-D-F-G-I |
c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D and G each one week. Which would you shorten? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.)
| B | |
| C | |
| D | |
| G | |
| E | |
| F |
d-1. What is the new critical path? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.)
| A-C-F-G-I | |
| A-B-E-I | |
| A-D-H-I | |
| A-D-F-G-I |
d-2. What is the earliest completion time for the new critical path?
Completion time weeks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
