Question: Only C & D please! Consider the following network diagram Below are the activity time estimates, in months. Activity Optimistic Most likely Pessimistic A 2

Only C & D please!

Consider the following network diagram

Only C & D please! Consider the following network

Below are the activity time estimates, in months.

Activity Optimistic Most likely Pessimistic
A 2 5 11
B 3 3 7
C 1 3 5
D 6 8 10
E 4 7 10

What is the expected duration of the activity A?

5.5 months

b. Refer to the network diagram in the previous question. What is the standard deviation of the duration of the path B-C-D?

2 months

c. What is the probability that the path A-D will be completed within 15 months?

0.1804

0.7111

0.7556

0.82

0.9138

Another value

Only C & D needed!

d. What is the probability that the project will be completed within 15 months? Assume that the path durations are independent of each other (though they are not), just like we did in the lecture.

0.36

0.3658

0.4613

0.5628

0.6136

Another value

Consider the following network diagram A E E B D

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!