Question: Problem 3 Consider the following information about a probabilistic project: Activity Immediate Predecessors Time (weeks) Optimistic Likely Pessimistic A 2 5 8 B A 2

Problem 3

Consider the following information about a probabilistic project:

Activity

Immediate Predecessors

Time (weeks)

Optimistic

Likely

Pessimistic

A

2

5

8

B

A

2

8

11

C

A

4

7

10

D

A

5

10

15

E

B

5

9

16

F

C

3

6

15

G

D

8

10

12

H

E, F, G

5

5

5

  1. Calculate the expected durations and the variance (or standard deviation) for each activity.
  2. What is the expected project completion time and the project standard deviation?
  3. What is the likelihood the project will be finished by week 32?
  4. If you wanted to be 99% confident of delivering the project on time, how much additional time would you need to add to the schedule?
  5. Problem 3 Consider the following information
Problem 3 Coeatader the following informaricen ahout a peobabilistic project: a. Calculate the expectad dusations and the variance (or ktandard deviation) for each activity - b. What is the expscted project completion time and the project standard deviatiou? c. What 15 the likelihood the project will be fimisoed by week 32

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!