Question: Problem 3 Consider the following information about a probabilistic project: Activity Immediate Predecessors Time (weeks) Optimistic Likely Pessimistic A 2 5 8 B A 2
Problem 3
Consider the following information about a probabilistic project:
| Activity | Immediate Predecessors | Time (weeks) | ||
| Optimistic | Likely | Pessimistic | ||
| A | 2 | 5 | 8 | |
| B | A | 2 | 8 | 11 |
| C | A | 4 | 7 | 10 |
| D | A | 5 | 10 | 15 |
| E | B | 5 | 9 | 16 |
| F | C | 3 | 6 | 15 |
| G | D | 8 | 10 | 12 |
| H | E, F, G | 5 | 5 | 5 |
- Calculate the expected durations and the variance (or standard deviation) for each activity.
- What is the expected project completion time and the project standard deviation?
- What is the likelihood the project will be finished by week 32?
- If you wanted to be 99% confident of delivering the project on time, how much additional time would you need to add to the schedule?