Question: *** ONLY NEED ASSISTANCE WITH E & F *** In preparing to teach a new course, the professor has determined that he will use six
*** ONLY NEED ASSISTANCE WITH E & F ***
In preparing to teach a new course, the professor has determined that he will use six activities. He has also estimated the activity times. A listing of the various activities required, their immediate predecessors, and estimates of their times (in days) is given below.
| Activity | Immediate Predecessors | Optimistic Time (Days) | Most Likely Time (Days) | Pessimistic Time (Days) |
| A | -- | 3 | 6 | 10 |
| B | A | 4 | 8 | 14 |
| C | A,B | 1 | 3 | 8 |
| D | B,C | 5 | 7 | 10 |
| E | C | 2 | 4 | 8 |
| F | D,E | 2 | 5 | 9 |
For any calculations you make related to time values, including any expected times and time standard deviations, calculate these values to 2 decimal places (xx.xx).
E. How many days should the marketing manager allow for completion of the critical path if he wants only a 5% chance that the critical path will be completed in more than this time?
F. What is the probability that the critical path will be completed in exactly 32 days?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts