Question: d) What is the probability that the critical path will be completed between 31 and 33 days? In preparing to teach a new course, the

d) What is the probability that the critical path will be completed between 31 and 33 days?
In preparing to teach a new course, the professor has determined that he will use six activities. He has also estimated the activity times. A listing of the various activities required, their immediate predecessors, and estimates of their times (in days) is given below. Activity Immediate Predecessors B D E F A AB B.C DE Optimistic Time (Days) 3 4 1 5 2 2 Most Likely Pessimistic Time (Days) Time (Days) 6 10 8 14 3 8 7 10 4 8 5 9 For any calculations you make related to time values, including any expected times and time standard deviations, calculate these values to 2 decimal places (xx.xx)Step by Step Solution