Question: ONLY NEED HELP WITH E F & G The Action Toy Company has decided to manufacture a new train set, the production of which is
ONLY NEED HELP WITH E F & G
The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is units per 40-hour workweek:
| Task | Performance Time (seconds) | Predecessors | |
| A | 22 | ||
| B | 30 | A | |
| C | 15 | A | |
| D | 15 | A | |
| E | 10 | B, C | |
| F | 28 | D, E | |
his exercise only contains parts b, c, d, e, and f.
b) Given the demand, the cycle time for the production of the new train set = 30 seconds (round your response to one decimal place).
c) The theoretical minimum number of workstations= 4 (round your response up to the next whole number).
d) Using the longest operation time rule, the assignment of tasks to workstations should be: (Hint: Number workstations sequentially in terms of precedence relationships and combine any applicable tasks.)
| Task | Workstation # |
| A | Station 1 |
| B | Station 2 |
| C | Station 3 |
| D | Station 3 |
| E | Station 4 |
| F | Station 5 |
Were you able to assign all the tasks to the theoretical minimum number of workstations? No
e) The total idle time per cycle for the process = ???? seconds (enter your response as a whole number).
f) Efficiency with 5 work stations = ??? %
g) If 6 workstations used, efficiency = ??? %
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts