Question: A labor team for placing concrete consists of one labor foreman at $26 29 per our, one cement finisher at $29.30 per hour, 3

A labor team for placing concrete consists of one labor foreman at

A labor team for placing concrete consists of one labor foreman at $26 29 per our, one cement finisher at $29.30 per hour, 3 laborers at $24.45 per hour each, and one eqguipment operator at $34.5 per hour. They work for B-hour per day Detemmine the cost per day of this team Sample anewor format is 4,322

Step by Step Solution

3.54 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Solution Cost per day 1308 Explanation Cost per day ... View full answer