Question: Operation A Operation B Operation C A completed item Standard time = 4.2 min Standard time = 3.6 min Standard time = 4.9 min Three

Operation A Operation B Operation C A completed

Operation A Operation B Operation C A completed item Standard time = 4.2 min Standard time = 3.6 min Standard time = 4.9 min Three manufacturing operations occur in sequence, as depicted above. There is one shift per day, and it is 8 hours long. Answer next 4 questions using this sequence. If one operator is assigned to Operation A, one operator is assigned to Operation B, and one operator assigned to Operation C, how many items will be produced each day from this line? O 85.67 O 97.96 0 78.55 O 87.12