Question: OPERATIONS MANAGEMENT AND OPERATIONS RESEARCH QUESTION 1 Draw the activity-on-node (AON) project network associated with the following activities for Ewoenam's consulting company project. How long

OPERATIONS MANAGEMENT AND OPERATIONS RESEARCH

QUESTION 1

Draw the activity-on-node (AON) project network associated with the following activities for Ewoenam's consulting company project. How long should it take Ewoenam and her team to complete this project? What are the critical activities? Derive a table showing the ES, EF, LS, LF, Slack Time and Critical Path.

Activity

Immediate Predecessor(s)

Time (days)

A

-

3

B

A

4

C

A

6

D

B

6

E

B

4

F

C

4

G

D

6

H

E, F

8

QUESTION 2

Given the activities whose sequence is described by the following table, draw the appropriate activity-on-node (AON) network diagram.

Which activities are on the critical path?

What is the length of the critical path?

Activity

Immediate Predecessor(s)

Time (days)

A

-

5

B

A

2

C

A

4

D

B

5

E

B

5

F

C

5

G

E,F

2

H

D

3

I

G, H

5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!