Question: - 3 . 3 Draw the activity - on - node ( AON ) project network associated with the following activities for Dave Carhart's consulting
Draw the activityonnode AON project network associated with the following activities for Dave Carhart's consulting company project. How long should it take Dave and his team to complete this project? What are the critical path activities?
tableActivityImmediate PredecessorsTime daysABACADBEBFCGDHE F
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock