Question: OPERATIONS MANAGEMENT ASSIGNMENT #3 (Total 100 points) Due Friday, July 10, 2020 Question 1. (Total 50 points) Using the PERT/CPM solution technique, draw the precedence

OPERATIONS MANAGEMENT ASSIGNMENT #3 (Total 100
OPERATIONS MANAGEMENT ASSIGNMENT #3 (Total 100 points) Due Friday, July 10, 2020 Question 1. (Total 50 points) Using the PERT/CPM solution technique, draw the precedence diagram, determine the ES, EF, LF, LS and slack times for each activity listed below, identify the activities that are on the critical path and indicate the duration of the project. The indirect cost for the project is $2500 per day. Given the following information, determine an optimum crashing plan. What is the total cost for the plan? Activity Precedes Normal Duration (day) Crashing Potential Crash Cost per Day ($) 1 Start Start A B D E A B C,D E GF F F 1 1 5 4 4 2 6 3 3 5 4 1000 500 1200 1500 1000 1 1 - LUI H 1 - 2 800 1900 3000 - End 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!