Question: Operations Management: fice system that will improve word processing and interoffice communications for a particular company. Contained in the proposal is a list of activities

Operations Management:

  1. fice system that will improve word processing and interoffice communications for a particular company. Contained in the proposal is a list of activities that must be accomplished to:

Activity

Description

Immediate

Predecessor

Time (Weeks)

Cost ($1000)

Normal

Crash

Normal

Crash

A

Plan need

-

10

8

30

70

B

Order equipment

A

8

6

120

150

C

Install Equipment

B

10

7

100

160

D

Setup training lab

A

7

6

40

50

E

Conduct training cost

D

10

8

50

75

F

Test system

C, E

3

3

60

-

  1. Develop a project network.
  2. Develop an activity schedule.
  3. What are the critical activities, and what is the expected project completion time?
  4. Assume that the company wants to complete the project in six months or 26 weeks. What crashing decisions do you recommend to meet the desired completion time at the least possible cost? Work through the network and attempt to make the crashing decisions by inspection.
  5. Develop an activity schedule for the crashed project.
  6. What added project cost is required to meet the six-month completion time?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!