Question: OPS - In a simple project network consisting of three sequential activities, A , B , and C , where A directly precedes B ,

OPS - In a simple project network consisting of three sequential activities, A,B, and C, where A directly precedes B, and B directly precedes C, the durations of activities A,B, and C are 4,3, and 8 days, respectively. Which of the following statements accurately describes the critical path and its total duration?