Question: In a simple project network consisting of three sequential activities, A , B , and C , where A directly precedes B , and B

In a simple project network consisting of three sequential activities, A, B, and C, where A directly precedes B, and B directly precedes C, the durations of activities A, B, and C are 4,3, and 8 days, respectively. Which of the following statements accurately describes the critical path and its total duration?
Group of answer choices
The critical path is A-B-C with a total duration of 15 days
The critical path is B-C with a total duration of 11 days
The network does not have a critical path
The critical path is A-B-C with a total duration of 11 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!