Question: Optimistic Most Likely Pessimistic Immediate Predecessor(s) Time (week) Time(week) Time(week) 6 9 12 A 4 7 10 C A 2 3 8 D B 3

Optimistic Most Likely Pessimistic Immediate

Optimistic Most Likely Pessimistic Immediate Predecessor(s) Time (week) Time(week) Time(week) 6 9 12 A 4 7 10 C A 2 3 8 D B 3 6 9 E B 6 9 12 F C 1 4 7 G E.E 3 6 9 H D 2 5 8 I G.H 1 3 7 Considering the most likely time estimates what is the critical path of the project? Considering the most likely time estimates what is the project completion time? Considering optimistic, most likely and pessimistic time estimates what is the activity variance along the critical path? What is the probability of completion of the project before week 36? Activity ABU