Question: Question 2 0 / 1 point The following are typical characteristics of a Deployment project EXCEPT _ _ _ _ _ _ ? Question options:

Question 20/1 point
The following are typical characteristics of a Deployment project EXCEPT______?
Question options:
a) Uncertainty reduction as a measure of progress and performance
b) Cost (Budget)
c) Simple Life cycle model
d) Deterministic time values
Question 30/1 point
A project life cycle is made of the following?
Question options:
a) Estimates
b) Work breakdown structure
c) Phases
d) Milestones
Question 160/1 point
Which of the following is a means of monitoring and controlling the project costs and activities?
Question options:
a) A work breakdown structure
b) PERT analysis
c) A checklist at a project's milestone
d) A work breakdown structure
e) A Gantt charts
Question 320/1 point
A project has three paths with the following time duration in days.
A-B-C-D has 25 days. A-E-C-D has 20 days and A-F-D has a 21 days.
Which of the following statements is TRUE?
Question options:
a) A-F-D is the shortest path and the critical path
b) The expected duration of this project is 25days.
c) A-E-C-D has 20 days, so it is the shortest time it will take this project to finish
d) The expected duration is 25+20+21=66 days
Question 340/1 point
For our one-day event, which of the following stakeholder is the MOST important?
Question options:
a) The customer
b) The CEO
c) The project manager
d) The project sponsor
Question 370/1 point
Which of the following is NOT a Deliverable statement?
Question options:
a) A 50x50 garden with 3 benches and a free-standing hammock
b) Heat sinking fan is not included but connectors are included
c) Kitchen appliances to include microwave oven, dishwasher, integrated cooker with Wi-Fi
d) An open day events
e) A promotional video for a product launch
Question 390/1 point
If the interest rate for a saving account is 5%, which of the following required rate of return may entice an investor to undertake a project?
Question options:
a) At least 5%
b) At least 10%
c) At least 2.5%
d) At least 5.5%
e) At least 0.5%
Question 410/1 point
Your organisation is setting up super-fast broadband and Virtual Private Networks (VPN) in the home of all its employee so that they can work remotely. The table below is the project information.
Activities Predecessor(s) Duration (days)
A -2
B A 15
C A 10
D A 13
E A 18
F C, D 15
G B, F 10
H G, E 5
The Project Board will also like to know how long it will take to complete this project?
Note: The project team can ONLY work 5 days a week, (Monday-Friday) and the project Board assumes the projects starts on a Monday.
Question options:
a)9 weeks
b)45 weeks
c)8 weeks and 2 days
d)5 weeks
e)6 weeks and 2 days
Question 460/1 point
Activity
Optimistic
Most likely Pessimistic Immediate predecessor
A 345--
B 579--
C 2310 A
D 258 B
E 177 B
F 357 C,D
G 789 D,E
H 2610 F
What is the critical path of this project?
Question options:
a) B-D-G-F-H
b) A-C-F-H
c) B-D-F-H
d) B-D-F-G-H
Question 500/1 point
How many days can activity C be delayed without changing the whole project's earliest completion time?
Activity Predecessor Time(days)
A -8
B -6
C -3
D A,B 10
E C 8
F A 5
G D,E 3
H G 4
Question options:
a)0 days
b)5 days
c)7 days
d)2 days
Question 540/1 point
An organisation wants to improve the quality of its service and aware that this undertaking need to be managed as a project. The requirements are understood but there is moderate-to-high risk. Which of the PLCs would you use to organise the project processes/phases?
Question options:
a) Spiral/Prototype PLC
b) S-Curve PLC
c) J-Curve PLC
d) Iterative PLC
Question 550/1 point
A project manager has a problem with a team members performance. What is the best form of communication for addressing this problem?
Question options:
a) informal verbal communication
b) Formal verbal communication
c) Informal written communication
d) Formal written communication
Question 560/1 point
When projects fail, it typically happen_____
Question options:
a) Towards the end of the PLC
b) At the beginning of PLC because of poor scope
c) In the middle of a PLC during execution of the plan
d) Because the Project Manager is a graduate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!