Question: Order Point = DDLT +SS DDLT= Demand During Lead time SS= Safety Stock Safety stock is one standard deviation and one standard deviation = 200

Order Point = DDLT +SS

DDLT= Demand During Lead time

SS= Safety Stock

Safety stock is one standard deviation and one standard deviation = 200 units.

Calculate Order Point if DDLT is 1000 units. Also calculate order pint when safety stock is 2 standard deviations.

What is the safety stock if Order point is 3000 and demand during demand during lead time is 2000 units?